Minutes:
  I decided to extend the Construction3 Iteration by 1 week and delay
Transition phase by 1 week so it ends during Exam week. This should be
ok because I anticipate tasking for transition to be light.
  All programming tasks should be completed by the next meeting in
preparation for the termination of Construction3.

Tasking:
  Larry - progress continuing on New Diagram stuff. 2 days.
  Uday - Working on Schema PersistenceDelegates for save/load. By
Friday
  Schoudel - working on UI enhancements for Zoom. By next mtg
  Jim - work with Sandra to refactor layout algorithm. Make metrics
        reports.
  Ross - Continue working on bug squashing
  Sid - Continue working on Save/Load stuff with Uday
  Sandra - Refactor Autolayout stuff with Jim. Increase table spacing.